Tongs Street, Finley - Drainage Works
- Project typeDrainage upgrade
- Contractor nameCrawford Civil
Berrigan Shire Council, will be undertaking essential infrastructure works at the intersection of Tongs Street and Murray Street, Finley. These works involve the installation of concrete pipe, pits and associated civil works as part of Council’s ongoing commitment to improve stormwater drainage and road infrastructure.
Personal access to homes and businesses will be maintained; however, vehicle access may be restricted at times. Crawford Civil will contact affected property owners individually ahead of any disruptions. Traffic management and detour routes will be in place as required to ensure the safety of all road users, and we ask that you follow all signage and directions from traffic controllers. Rubbish collection services will continue as usual, and all relevant emergency services have been notified to ensure access is maintained where required.
Detail of proposed work:
Location: Tongs Street, Finley
Estimated Start Date: Monday, 26 May 2025 (weather permitting)
Working Hours: 7:00am to 6:00pm, each day
Expected Duration: Approximately 2 weeks, weather permitting